2014 Bond Sub Goal #3.1: Upgrade Fiber and Cabling Connectivity

This subgoal is the portion of the Long Range Planning Committee's Recommendation #3 which includes upgrading network cabling, fiber optic connectivity, and network closets in the schools, service centers, hub connections, and data centers that will expand the access for faster connectivity

Weekly Updates

October 3, 2017 District Wide Area Network Fiber Design Detailed Analysis of Options
September 25, 2017 District Wide Area Network Fiber Design Analysis of Options
September 15, 2017 Meeting with Pure Speed Lightwave to Discuss Contracts
August 17, 2017 Meeting with Pure Speed Lightwave to Discuss Fiber Design Options
August 9, 2017 Meeting with Phonoscope to Discuss Implementation of RFP 17-01-5080
June 26, 2017 Cabling for Wireless and VoIP Nearing Completion at the Service Centers
June 16, 2017 Cabling for High-Speed Wireless and New VoIP Phones Continue at the Services Centers
June 13, 2017 District network Expansion Status to Fiber Connectivity to New Schools
June 1, 2017 High Speed Cabling for Wireless and VoIP Continues at the ISC
May 25, 2017 District Network Expansion Status of Fiber Connectivity to New Schools
May 19, 2017 Cabling for High-Speed Wireless and New VoIP Phones Begins at the ISC
April 18, 2017 District Network Expansion Status of Fiber Connectivity to New Schools
February 7, 2017 RFP Submission and Fiber Network Buildout
November 4, 2016 RFPs Submission Timeline is Set Working to Expand the Network
November 1, 2016 Enterprise WAN Build-Out to Connect New Sites Expands
November 1, 2016 Network Expansion Meeting with EPS
October 3, 2016 - Pope Elementary Connected to the District's Wide Area Network
September 30, 2016 - Fiber Network Build-Out Status of Hub #7
September 30, 2016 - Fiber Network Building Planning of Hub #7
September 22, 2016 - Fiber Network Build-Out Status of Hub #7
September 1, 2016 - District Network Build-Out to Connect New Sites
August 10, 2016 - Enterprise Wide Area Network Expanding to a 7th Hub 
June 3, 2016 - High-Speed Wireless Cabling Projects Continue Through the Summer
April 27, 2016 - Design Meeting with Phonoscope for Future Fiber
April 15, 2016 - Visit to Frazier Elementary to Assess Progress
March 24, 2016 - Cy Woods HUB Complete
March 10, 2016 - Cy Woods and Cy Ridge HUB Connection Status
February 19, 2016 - Elementary Cabling Schedule
January 4, 2016 - Cabling Progress
December 11, 2015 - Cy Ridge Hubble Box Falls
October 28, 2015 
October 23, 2015 - Cabling Progress
October 16, 2015 - Cabling Progress
October 2, 2015 
October 2, 2015 - CyWoods 
September 21, 2015 
September 21, 2015 - Cable Schedule
September 18, 2015 
September 11, 2015 - Status
September 11, 2015 - Cabling Schedule
August 31, 2015 - Cabling Status
August 23, 2015 - Cabling Status
August 21, 2015 - Cabling Schedule
August 17, 2015 - Cabling Status
August 17, 2015 - Cabling Schedule
August 5, 2015 - Cabling Status
August 3, 2015 - Cabling Status
July 30, 2015 - Fiber Connectivity Schedule
July 29, 2015 - Cabling Schedule
July 22, 2015 - Fiber Connectivity Schedule
July 20, 2015 - Cabling Schedule
July 17, 2015 - Cabling iSphere Report
July 17, 2015 - Cabling Status
July 3, 2015
June 26, 2015
June 19, 2015
June 11, 2015
June 5, 2015
August 23, 2017 - Cabling Issues - Visit to Aragon Middle School
August 25, 2017 Cabling Commscope Separator Tape
August 23, 2017 Cabling Issues with Plastic Removal - Schedule for Resolution
December 2, 2016 Cabling Report
November 4, 2016 Cabling Report
October 28, 2016 - Cabling Report
October 21, 2016 - Cabling Report
September 30, 2016 Cabling Report
September 16, 2016 Cabling Report
August 26, 2016 Cabling Report
August 19, 2016 Cabling Report
August 12, 2016 Cabling Report
August 5, 2016 Cabling Report
July 29, 2016 Cabling Report
July 22, 2016 Cabling Report
July 15, 2016 Cabling Report
July 8, 2016 Cabling Report
July 1, 2016 - Cabling Report
June 24, 2016 Cabling Report
June 17, 2016 Cabling Report
June 10, 2016 Cabling Report
June 3, 2016 Cabling Report
May 27, 2016 Cabling Report
May 20, 2016 Cabling Report
May 13, 2016 Cabling Report
May 6, 2016 Cabling Report
April 29, 2016 Cabling Report
April 22, 2016 Cabling Report
April 15, 2016 Cabling Report
April 8, 2016 Cabling Report
April 1, 2016 Cabling Report
March 24, 2016 Cabling Report
March 18, 2016 Cabling Report
March 4, 2016 - Cabling Report
February 26, 2016 - Cabling Report
February 19, 2016 - Cabling Report
February 12, 2016 - Cabling Report
February 5, 2016 - Cabling Report
January 29, 2016 - Cabling Report
January 25, 2016 - Cabling Report
January 19, 2016 - Cabling report
January 8, 2016
December 31, 2015
December 11, 2015
November 13, 2015
November 6, 2015
October  30, 2015
October 23, 2015 
October 16, 2015 
October 9, 2015 
October 2, 2015 
Powered by Create your own unique website with customizable templates.